Main St. Traffic impact due to known Construction activities. 

Sewer Separation: Main St. from Mercer to Berry (Contractor – New Prince, Engineer and Inspector – Suburban):

  • Monday, Tuesday and Wednesday – various punch list items.  This will be a mobile operation from Mercer Street up to Berry Street.  Work will be in areas already under police traffic control and do not anticipate the need for an officer.

2-way Conversion/Paving Main Street Berry to Ward

  • Saturday 11/21/20 Berry to Ward will be closed for striping, two officers for traffic control and NO PARKING signs posted on both sides of Main Street for the entire area. After striping is completed temporary cones/drums with allowance for parking between Ward and Berry will be installed to keep the current traffic pattern in place until signal work on Monday.
  • Monday HBC and Signal Controls will be activating signals.  Main Street will be 2 way from Berry to Anderson

Streetscape:  Main St. Atlantic to Berry (Contractor – Cifelli & Son, Engineer and Inspector – Suburban):

  • Monday through Wednesday Atlantic to Mercer will be closed for streetscape work
  • Monday through Wednesday Camden to Berry will be closed for Streetscape work

SUEZ water main replacement (Contractor – J. Fletcher Creamer)

  • Saturday 11/21/20 Salem to Camden will be closed for water main replacement
  • Monday through Wednesday Salem to Camden will be closed for water main replacement

Signalization:  Main St. @ Demarest, Berry & Salem  (Contractor – HBC, Engineer and Inspector – Suburban):

  • Monday HBC and Signal Controls will be activating signals.  Main Street will be 2 way from Berry to Anderson 

Signalization:  Main St. & Mercer (Contractor – JC Contracting, Engineer and Inspector – Boswell):