December Construction Update

For your information and distribution, please find the Main St. Traffic impact due to known Construction activities.

Streetscape:  Main St. Atlantic to Berry (Contractor – Cifelli & Son, Engineer and Inspector – Suburban):

  • Atlantic to Mercer full closure finish paver install, continue temporary pavement restoration and clean up
  • Salem to Camden full closure  curb install

SUEZ water main replacement (Contractor – J. Fletcher Creamer)

  • Atlantic to Mercer full closure installing services
  • Salem to Camden full closure installing services

Signalization:  Main St. & Mercer (Contractor – JC Contracting, Engineer and Inspector – Boswell):

  • No impact to traffic flow.

2 way Conversion/Paving Main Street Berry to Ward

  • No activity scheduled

Signalization:  Main St. @ Demarest, Berry & Salem  (Contractor – HBC, Engineer and Inspector – Suburban):

  • No activity scheduled

Sewer Separation: Main St. from Mercer to Berry (Contractor – New Prince, Engineer and Inspector – Suburban):

  • No impact to traffic flow